Please, turn device

into a horizontal position for better use of our website

For a more comfortable site usage, please, upgrade your browser to a more current version

103 Soborna Str., Sophiyivska Borshchahivka, Kyiv region +380 44 331-26-26

All news

21.06.2017

Construction process:

2nd line

103/8 - facade work continues, executed by 95%; Installation of sewage, storm water drainage continues; Installation of window drainage is done by 90%;

103/9 - heating, water - ready from 1 to 6 floors; Lifts are mounted on 95%. Execution of facade works, executed on 70%, completed the screed from the basement on 6 floors.

103/10 (1) - facade readiness - 20%

103/10 (2) - facade readiness - 50%; Readiness of water supply, heating - 80%, installation of curtains on ventilation ducts continues.

103/10 (3) - work on the installation of the facade continues; The readiness of window drafts is 55%, installation of curtain on ventilation ducts has been completed.

3rd turn

103/11 (2) - concreting of the floor slabs of the 5th floor;

103/11 (3) - installation of the formwork of the ceiling of the 5th floor;

103/12 (1) - 5th floor laying;

103/12 (2) - the brick-laying of the 5th floor has been completed;

103/13 (1) - the laying of the 5th floor was completed, the installation of the formwork of the 5th floor was completed

103/13 (2) - concreting of the ceiling of the 4th floor is completed; The laying on the 5th floor is underway

103/14 - the laying on the 4th floor is completed;

103/15 (1) - the concreting of the ceiling of the 3rd floor was completed, and the laying of the 4th floor was started

103/15 (2) - completed the brickwork on the 4th floor. Work is under way to install the ceiling of the 4th floor

4th turn

103/19 - laying of walls of the first floor of both buildings

103/16 - the process of brick masonry of external and internal walls of the first floor of one case is carried out, installation of overhead panels of a basement of one case is made;

103/17 - installation of foundation blocks was performed, concreting of the monolithic belt of the basement floor

103/18 (1) - corner section - concreting of the foundation foundation is performed; in the second section - mounting of the foundation is carried out. Blocks

103/18 (2) - installation of the foundation has begun. Blocks

Also, work is ongoing on the installation of fencing along the road, the installation of sewage and water supply throughout the queues

Tell your friends

Do you have a question?

Please, provide your name and phone number and our manager will call you soon.

Thank you!

Your message was successfully sent.