12.06.2017

Construction process:

2nd stage:

103/8 - sewage from 1 to 6 floor mounted, storm sewer - similar. Facade work continues, executed by 80%; The roof of the house is made by 90%. Installation of window drainage is done by 70%; 100% ready ventilation ducts.

103/9 - sewerage from 1 to 6 floor mounted, storm sewer is also ready from 1 to 6 floor. Heating, water - ready from 2 to 6 floors; Lifts are mounted on 95%. The facade works are completed, completed by 40%, completed the screed from 2 to 4 floor.

103/10 (1) - ready sewage from 1 to 6 floors, storm - similarly. Heating, water - finished with 1 to 6 floors, the readiness of the facade - 10%, completed the screed from 2 to 5 floor. The roof is 80% ready.

103/10 (2) - sewage is ready from 1 to 6 floor ready, storm sewage - similarly. Window tiles are ready for 20%, facade - 35%, ventilation ducts by 45%.

103/10 (3) - the sewage is ready from the 1st to the 6th floor, the storm is similar. Water, heating - ready from 1 to 6 floors. Elevator is mounted, the facade is ready for use - 60%, window drafts - 45%, completed basement recess, 2-6 floors; Ventilation ducts are ready for 45%

3rd stage:

103/11 (1) - finishing the laying on the 6th floor;

103/11 (2) - finish work on reinforcement of the floor slab of the 5th floor;

103/11 (3) - the laying of the 5th floor continues;

103/12 (1) - finish the laying on the 5th floor;

103/12 (2) - continue the brickwork on the 5th floor;

103/13 (1) - the installation of floor slabs continues on the 5th floor;

103/13 (2) - the process of installation of slabs over the 4th floor continues;

103/14 - the laying of the 4th floor began;

103/15 (1) - complete the installation of floor slabs above the 3rd floor; 103/15 (2) - finish the brickwork on the 4th floor.

4th stage:

103/16 - the process of brick masonry of external and internal walls of the first floor started, installation of ceiling panels on the ground floor;

103/18 - the process of wall mounting of the ground floor started;

103/19 - brickwork of external and internal walls of the first floor is executed.