29.05.2017

Constructions progress

Building of 2nd stage – facade work is finish. Building 103/10 – make a screed on the roof.

3th stage:

103/11(1) - brick laying on 6 floor, (2) – mounting of the slab above the 5th floor, (3) - brick laying on 3 floor, also perform internal partitions of 3 floors,

103/12(1) - brick laying on 5 floor, (2) - mounting of the slab above the 4th floor,

103/13(1) - brick laying on 5 floor finished, formwork for slabs is ready, also perform internal partitions of 3 floors, (2) - brick laying on 5 floor finished, mounting of the slab is start,

103/14 - mounting of the slab above the 3th floor, also perform internal partitions of 13 floors,

103/15(1) - brick laying on 3 floor finished, ready formwork, also perform internal partitions of 2 floors. (2) - brick laying on 4 floor.

4th stage:

103/16 – mounting of the slab above the ground floor,

103/17 - the reinforcement of the monolithic belt,

103/18(1) - mounting foundation blocks, (2) - foundation blocks are ready,

103/19 brick laying finished.