30.03.2017

Course of construction

2nd stage:

House 103/8 - work is continuing on the electrical wiring in the house.

In the house 103/9 - plumbing works are carried out, also carry out roofing works, install windows. Finish work on arranging entrance groups (the entrance part of the house).

3 line:

In the house 103/11 (section 1), laying of the fifth floor is carried out.

In Section 2 of 103/11, a slab is formed over the 4th floor.

In the 3 sections of the house 103/11, brickwork of the 5th floor is carried out.

House 103/12 in the 1st and 2nd sections are laid 4 floors.

In the house 103/13 (section 1), the laying of the 4th floor is carried out.

House 103/13 (2 section) at the stage of overlapping the slab of the 3rd floor.

In the house 103/14 and 103/15 (1 section) work is carried out on the laying of the 3 floors. In section 2 of the house 103/15 overlap the 3rd floor.

Also, in all houses form interior partitions.

4 turn:

House 19 is 100% overlapped basement floor. The monolith is filled.

In house 18 (section 1) - a monolithic belt and foundation works are made.

House 18 (section 2) - completed on a 100% foundation stage of the house.

In the house 17 - foundation walls are ready.

House 16 - performed work on the basement floor, flooded with a monolithic belt.