27.04.2017

Course of construction:

House 103/8 - wiring to the apartments. In the houses 103/9 the process of installing the windows was completed, in 103/8 and 103/10 - the work was completed by 90%.

House 103/9 and 103/10 conducted wiring in the apartments and MZK. Also, in houses 103/9 and 103/10 (section B and F), work is continuing on the distribution of water supply and heating.

Plastering works are continuing in the house 103/8 (completed by 25%), 103/9 and 103/10 - by 90%. Facade works in houses 103/8 are executed on 7%, 103/9 - on 7%, 103/10 - on 20%.

Continuing gas in homes.