05.05.2017

Course of construction:

The second stage:

House 103/8 - face work done by 30%. In homes 103/8, 103/9, 103/10 Plaster work done by 95%. In homes 103/10 (First Section) 3-5 floors 103/10 (Third Section) - 4-5 floors 3-5 103/9 floors completed installation of utilities. Internal wiring - the work is done by 90% of all homes 2 turns. The house 103/10 (First Section) 103/9 and completed installation of elevators.

Third stage:

House 103/11 (Second Section, 5th floor), 103/13 (First Section, 4th floor), 103/15 (Second Section, 3rd floor) - continues clutch.

Fourth stage:

103/18 House - filled one section of the foundation.