02.03.2017

Сonstruction Progress

Stage 2:

The house is 103/10 - The works on the wiring Electricity Condominium.

The house 103/9 - Perform masonry parapets. Spend Floor Electricity.

The house 103/8 complete laying bricks on a staircase.

Phase 3:

The house, finished a 103/15 laying 2 floors. Go to work on the 3 floor. Floor slabs.

The house is now complete laying 103/14 2 floors.

House 103/13 - masonry wall 3 floors.

House 103/13 (2 section) - complete laying 2 floors.

House 103/11 (1 section) - Work on laying the 4th floor.

House 103/11 (2 and 3 section) for the dynamics of the construction of this house on one level. Complete robots for laying 3 floors.

The house 103/12 (1 section) complete laying 3 floors.

In section 2 103/12 house complete overlap of 3 floors.

4 place:

House 19 - floor basement of the device.

House 16 - carried out the installation of the basement walls of the ground floor.

House 17 - Installation of basement walls of the ground floor.

House 18/1 - are working to seal the pit foundations.

House 18/2 - excavation device.