10.10.2017

Building progress of the 2nd & the 3d line 6.10.17

2nd stage All the buildings are carried out with the accomplishment of the territory.

House 103/8

installation works of the elevator are carried out

work on the installation of the roof, as well as parapet coverings, is completed

  • 100% tiled on balconies
  • the process of internal gasification of the house is being carried out
  • finishing works are continuing
  • installation of apartment doors is carried out
  • work on the manufacture of metal balconies is underway
  • House 103/9

    The work on connecting the house to external networks of VC is completed

    at the final stage of work on floor heating 1 floor

  • Foundation works on the building started
  • Electrical installation work in the basement is underway
  • Finishing works are under way
  • Cable-to-house cable line is installed
  • House 103/10 (1)

    at the final stage of the facade work

    lifts the lift

    work is ongoing on the placement of apartment doors

  • work on the installation of VK networks has been completed
  • the floor of the 1st floor is continued
  • finishing works at the house are carried out
  • At the final stage of work on the installation of floor screed 1 p
  • work on laying slopes 1 - 6 p
  • Cable-to-house cable line is installed
  • installation work on heating devices has been performed
  • House103/10 (2)

    work on decoration of places of public use is underway

    work on the laying of a floor screed (basement) is completed

  • installation of an elevator
  • The apartment door was imported and the installation started
  • House 103/10 (3)

    house finishing works are under way

  • installation of fixtures in public places (IZK)
  • 3rd line:

    House 103/11

    Electricity power grids continue to work,

    1 section completed installation of shibel

  • At the final stage of the implementation of interiors partitions
  • in 1 section completed, and 2 continues work on the construction of parapets of the roof
  • 2nd section on the 4th floor completes the interiors partitions
  • 2nd section of work on installation of shibles
  • Section 3 began work on the construction of roof parapets
  • 3 sections complete the installation of Vent. blocks
  • 103/12
  • 1 section was started overlay floor 5
  • 103/13
  • 2 sections complete the ceiling of the 6th floor
  • installation of ventilation units

    103/15

  • 1 - the 5th floor masonry continues
  • 4th turn

    House 19

  • work on insulation of the ground floor is underway
  • backfilling of the basement floor is carried out
  • House 16
  • work on insulation of the ground floor is underway
  • backfilling of the basement floor is carried out
  • Overlapping of one of the sections of the basement floor is executed
  • House 17
  • Overlapping of the ground floor of the building was completed
  • House 18/1, 18/2
  • work on insulation of the ground floor is underway
  • backfilling of the basement floor is carried out